Search
Find a document, activity or package
Practical queries work: floor tile WIR, material inspection, ACT-130, TAB, O&M.
773 results
Documents 618
Open in the document registerChecklistACT-013
Site Clearance and Grubbing — Inspection Checklist
Site Clearance and Grubbing · Civil
Inspection and Test PlanACT-013
Site Clearance and Grubbing — Inspection and Test Plan
Site Clearance and Grubbing · Civil
Method StatementACT-013
Site Clearance and Grubbing Method Statement
Site Clearance and Grubbing · Civil
Risk AssessmentACT-013
Site Clearance and Grubbing — Risk Assessment
Site Clearance and Grubbing · Civil
ChecklistACT-014
Excavation Works — Inspection Checklist
Excavation Works · Civil
Inspection and Test PlanACT-014
Excavation Works — Inspection and Test Plan
Excavation Works · Civil
Method StatementACT-014
Excavation Works Method Statement
Excavation Works · Civil
Risk AssessmentACT-014
Excavation Works — Risk Assessment
Excavation Works · Civil
ChecklistACT-015
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) — Inspection Checklist
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) · Civil
Inspection and Test PlanACT-015
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) — Inspection and Test Plan
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) · Civil
Method StatementACT-015
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) Method Statement
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) · Civil
Risk AssessmentACT-015
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) — Risk Assessment
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles) · Civil
ChecklistACT-016
Diaphragm Wall Construction — Inspection Checklist
Diaphragm Wall Construction · Civil
Inspection and Test PlanACT-016
Diaphragm Wall Construction — Inspection and Test Plan
Diaphragm Wall Construction · Civil
Method StatementACT-016
Diaphragm Wall Construction Method Statement
Diaphragm Wall Construction · Civil
Risk AssessmentACT-016
Diaphragm Wall Construction — Risk Assessment
Diaphragm Wall Construction · Civil
ChecklistACT-017
Dewatering Works — Inspection Checklist
Dewatering Works · Civil
Inspection and Test PlanACT-017
Dewatering Works — Inspection and Test Plan
Dewatering Works · Civil
Method StatementACT-017
Dewatering Works Method Statement
Dewatering Works · Civil
Risk AssessmentACT-017
Dewatering Works — Risk Assessment
Dewatering Works · Civil
ChecklistACT-018
Bored Piling Works — Inspection Checklist
Bored Piling Works · Civil
Inspection and Test PlanACT-018
Bored Piling Works — Inspection and Test Plan
Bored Piling Works · Civil
Method StatementACT-018
Bored Piling Works Method Statement
Bored Piling Works · Civil
Risk AssessmentACT-018
Bored Piling Works — Risk Assessment
Bored Piling Works · Civil
ChecklistACT-019
Pile Load Testing (Static / Dynamic) — Inspection Checklist
Pile Load Testing (Static / Dynamic) · Civil
Inspection and Test PlanACT-019
Pile Load Testing (Static / Dynamic) — Inspection and Test Plan
Pile Load Testing (Static / Dynamic) · Civil
Method StatementACT-019
Pile Load Testing (Static / Dynamic) Method Statement
Pile Load Testing (Static / Dynamic) · Civil
Risk AssessmentACT-019
Pile Load Testing (Static / Dynamic) — Risk Assessment
Pile Load Testing (Static / Dynamic) · Civil
ChecklistACT-020
Pile Integrity Testing — Inspection Checklist
Pile Integrity Testing · Civil
Inspection and Test PlanACT-020
Pile Integrity Testing — Inspection and Test Plan
Pile Integrity Testing · Civil
Activities 152
Site Clearance and Grubbing
Civil · During Construction
Excavation Works
Civil · During Construction
Shoring Works (Sheet Piles / Secant Piles / Contiguous Piles)
Civil · During Construction
Diaphragm Wall Construction
Civil · During Construction
Dewatering Works
Civil · During Construction
Bored Piling Works
Civil · During Construction
Pile Load Testing (Static / Dynamic)
Civil · During Construction
Pile Integrity Testing
Civil · During Construction
Pile Head Cutting and Trimming
Civil · During Construction
Packages 3
Floor and wet-area finishes
Screeding, porcelain floor tiling and wet-area waterproofing, from method statement through inspection records.
Foundations and concrete quality
Pile integrity testing, concrete pouring inspection and roof waterproofing records for the structural package.
Services inspections
Material receipt for the air handling units, switchgear inspection and duct leakage testing.