ACT-016 / ITP / R00
Diaphragm Wall Construction — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Release guide walls | — | — | — | — | — |
| Verify panel excavation | — | — | — | — | — |
| Coordinate reinforcement cage and specialist concreting | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: grab, support fluid, cage and tremie
Inspection sequence
- Release guide walls
- Verify panel excavation
- Coordinate reinforcement cage and specialist concreting
Inspection controls
- Depth, verticality, support-fluid properties and panel concrete volumes
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________