ACT-019 / CHK / R00
Pile Load Testing (Static / Dynamic) — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Identify test pile | — | — | — | — | — |
| Obtain specialist setup release | — | — | — | — | — |
| Witness approved load programme | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: approved reaction or dynamic test equipment
Inspection points
- Identify test pile
- Obtain specialist setup release
- Witness approved load programme
Records and release
- Load/displacement or dynamic trace, timestamps and engineer disposition
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________