Handover / CloseoutACT-170-CLOSEOUTR00Available

Final Handover Dossier Acceptance Index

Project HandoverCommissioning and Handover

ACT-170 / CLOSEOUT / R00

Final Handover Dossier Acceptance Index

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Dossier register
Handover itemReferenceRevisionAcceptance referenceOwnerDue dateRemarks
As-built drawings——————
O&M manuals——————
BIM deliverables——————
Maintainable asset register——————
Authority certificates——————
Commissioning records——————
Training——————
Warranties——————
Spares and attic stock——————
Keys——————
Outstanding defects——————

Dossier contents

  • Package reference / contract area / cutoff date / recipient: ____________________
  • Record current revision and acceptance reference for as-builts, O&M, BIM data, asset registers, authority certificates and commissioning records.
  • Verify training, warranties, spares, keys, remaining defects and agreed exclusions have named owners and dates.

Transfer acknowledgement

  • Transfer date / delivery location / outstanding obligations / receipt evidence: ____________________
  • Contractor, consultant and client acknowledgement and dates: ____________________