ACT-131 / ITP / R00
MV Cable Installation and Testing — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Verify cable and certified accessories | — | — | — | — | — |
| Witness approved pull and terminations | — | — | — | — | — |
| Get test release | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: MV cables, pulling gear and specialist test instruments
Inspection sequence
- Verify cable and certified accessories
- Witness approved pull and terminations
- Get test release
Inspection controls
- Drum lengths, pulling log and pre-energisation certificates
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________