ACT-087 / MS / R00
Stone Cladding (Dry Fix) Method Statement
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
Scope and project location
- Activity: Stone Cladding (Dry Fix). Discipline: Façade & Building Envelope.
- Applicable work limits / project / area / grid / exclusions: ____________________
Approved references and technical limits
- Drawing and revision / specification clause / approved ITP: ____________________
- Approved engineering design / manufacturer procedure / technical limits / project instructions where applicable: ____________________
- Permits / isolations / specialist and authority releases as applicable: ____________________
Responsibilities and resources
- Supervisor / specialist lead / safety lead / QC / consultant witness: ____________________
- Materials and equipment: stone panels, brackets, anchors and shims.
- Approved submittals / equipment IDs and calibration: ____________________
Prerequisites and work sequence
- Prior-work release / interfaces / access / pre-task briefing: ____________________
- 1. Survey supports.
- 2. Inspect fixings.
- 3. Align stone preserving cavity and movement joints.
Inspection stages and required records
- Checks and evidence: Stone batch, anchor tests, restraint and final survey.
- Before / during / final inspection: area, acceptance clause, frequency, hold or witness point and record reference: ____________________
- Nonconformance / corrective action / retest reference: ____________________
Approval
- Prepared by / reviewed by / approved by / signatures and dates: ____________________