ACT-048 / CHK / R00
Shear Walls and Lift Cores — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Transfer core controls | — | — | — | — | — |
| Verify cage and openings | — | — | — | — | — |
| Survey each lift after stripping | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: survey targets, rebar and opening formers
Inspection points
- Transfer core controls
- Verify cage and openings
- Survey each lift after stripping
Records and release
- Core verticality, shaft dimensions and embedded brackets
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________