ACT-166 / RA / R00
Snagging and De-snagging — Risk Assessment
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Task | Hazard and persons exposed | Initial risk | Controls | Owner | Residual risk |
|---|---|---|---|---|---|
| Walk by zone | — | — | — | — | — |
| Classify and assign defects | — | — | — | — | — |
| Verify before closing each item | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: snag register, zone drawings and evidence capture
Task risk review
- Walk by zone
- Classify and assign defects
- Verify before closing each item
Assessment prompts
- Assess interfaces relevant to this location: Live systems, occupancy and simultaneous commissioning activities.
- For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
- Briefing / permit reference / competent reviewer / approval date: ____________________