ACT-163 / MS / R00
Boundary Wall and Gates Method Statement
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
Scope and project location
- Activity: Boundary Wall and Gates. Discipline: External Works & Infrastructure.
- Applicable work limits / project / area / grid / exclusions: ____________________
Approved references and technical limits
- Drawing and revision / specification clause / approved ITP: ____________________
- Approved engineering design / manufacturer procedure / technical limits / project instructions where applicable: ____________________
- Permits / isolations / specialist and authority releases as applicable: ____________________
Responsibilities and resources
- Supervisor / specialist lead / safety lead / QC / consultant witness: ____________________
- Materials and equipment: boundary masonry, posts, gates and controls.
- Approved submittals / equipment IDs and calibration: ____________________
Prerequisites and work sequence
- Prior-work release / interfaces / access / pre-task briefing: ____________________
- 1. Confirm legal boundary.
- 2. Release supports.
- 3. Install wall and operational gates.
Inspection stages and required records
- Checks and evidence: Offsets, stability, clearance, safety devices and gate cycle.
- Before / during / final inspection: area, acceptance clause, frequency, hold or witness point and record reference: ____________________
- Nonconformance / corrective action / retest reference: ____________________
Approval
- Prepared by / reviewed by / approved by / signatures and dates: ____________________