Skip to content

Risk AssessmentACT-157-RAR00Available

Road Works (Sub-base / Base / Asphalt) — Risk Assessment

Road Works (Sub-base / Base / Asphalt)Infrastructure

ACT-157 / RA / R00

Road Works (Sub-base / Base / Asphalt) — Risk Assessment

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Risk Assessment worksheet
TaskHazard and persons exposedInitial riskControlsOwnerResidual risk
Release formation—————
Test base courses—————
Place and protect asphalt—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: aggregate, asphalt, compaction plant and survey tools

Task risk review

  • Release formation
  • Test base courses
  • Place and protect asphalt

Assessment prompts

  • Assess interfaces relevant to this location: Underground utilities, public access and mobile plant.
  • For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
  • Briefing / permit reference / competent reviewer / approval date: ____________________