ACT-155 / CHK / R00
Lift Shaft Preparation and Survey — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Transfer vertical datum | — | — | — | — | — |
| Survey each opening | — | — | — | — | — |
| Resolve deviations before handover | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: shaft survey instruments, benchmarks and opening schedule
Inspection points
- Transfer vertical datum
- Survey each opening
- Resolve deviations before handover
Records and release
- Pit, overhead, shaft plumb and embedded interfaces
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________