ACT-153 / RA / R00
Lift Installation — Risk Assessment
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Task | Hazard and persons exposed | Initial risk | Controls | Owner | Residual risk |
|---|---|---|---|---|---|
| Release shaft survey | — | — | — | — | — |
| Coordinate authorised installation | — | — | — | — | — |
| Obtain readiness inspection | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: lift rails, car, doors, drive and controller
Task risk review
- Release shaft survey
- Coordinate authorised installation
- Obtain readiness inspection
Assessment prompts
- Assess interfaces relevant to this location: Open shafts, moving equipment and stored energy.
- For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
- Briefing / permit reference / competent reviewer / approval date: ____________________