Inspection and Test PlanACT-123-ITPR00Available

FM200 / Clean Agent System — Inspection and Test Plan

FM200 / Clean Agent SystemFirefighting

ACT-123 / ITP / R00

FM200 / Clean Agent System — Inspection and Test Plan

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Release protected volume—————
Verify nozzle plan and circuits—————
Obtain specialist acceptance—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: listed agent cylinders, nozzles and controls

Inspection sequence

  • Release protected volume
  • Verify nozzle plan and circuits
  • Obtain specialist acceptance

Inspection controls

  • Cylinder IDs, enclosure integrity, abort and alarms; no unauthorised discharge
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________