ACT-115 / MS / R00
Grease Traps and Interceptors Method Statement
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
Scope and project location
- Activity: Grease Traps and Interceptors. Discipline: Plumbing & Drainage.
- Applicable work limits / project / area / grid / exclusions: ____________________
Approved references and technical limits
- Drawing and revision / specification clause / approved ITP: ____________________
- Approved engineering design / manufacturer procedure / technical limits / project instructions where applicable: ____________________
- Permits / isolations / specialist and authority releases as applicable: ____________________
Responsibilities and resources
- Supervisor / specialist lead / safety lead / QC / consultant witness: ____________________
- Materials and equipment: interceptor, covers, seals and vents.
- Approved submittals / equipment IDs and calibration: ____________________
Prerequisites and work sequence
- Prior-work release / interfaces / access / pre-task briefing: ____________________
- 1. Verify maintenance access and inverts.
- 2. Install and connect.
- 3. Inspect serviceability.
Inspection stages and required records
- Checks and evidence: Flow direction, cover rating, vents and leakage.
- Before / during / final inspection: area, acceptance clause, frequency, hold or witness point and record reference: ____________________
- Nonconformance / corrective action / retest reference: ____________________
Approval
- Prepared by / reviewed by / approved by / signatures and dates: ____________________