ACT-110 / CHK / R00
Storm Water Drainage — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Coordinate membrane flange | — | — | — | — | — |
| Verify slope and discharge | — | — | — | — | — |
| Witness controlled flow | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: outlets, strainers, stormwater pipes and supports
Inspection points
- Coordinate membrane flange
- Verify slope and discharge
- Witness controlled flow
Records and release
- Outlet ID, endpoint, ponding and leakage
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________