ACT-109 / RA / R00
Drainage and Soil Piping (uPVC / HDPE / Cast Iron) — Risk Assessment
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Task | Hazard and persons exposed | Initial risk | Controls | Owner | Residual risk |
|---|---|---|---|---|---|
| Coordinate falls and cleanouts | — | — | — | — | — |
| Join and support | — | — | — | — | — |
| Seal penetrations before enclosure | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: drainage pipe, fittings and acoustic supports
Task risk review
- Coordinate falls and cleanouts
- Join and support
- Seal penetrations before enclosure
Assessment prompts
- Assess interfaces relevant to this location: Stored pressure, contamination and access to pipework.
- For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
- Briefing / permit reference / competent reviewer / approval date: ____________________