Scope and project location
- Activity: Grilles, Diffusers and Dampers. Discipline: HVAC (Mechanical).
- Applicable work limits / project / area / grid / exclusions: ____________________
Approved references and technical limits
- Drawing and revision / specification clause / approved ITP: ____________________
- Approved engineering design / manufacturer procedure / technical limits / project instructions where applicable: ____________________
- Permits / isolations / specialist and authority releases as applicable: ____________________
Responsibilities and resources
- Supervisor / specialist lead / safety lead / QC / consultant witness: ____________________
- Materials and equipment: terminals, dampers, fixings and access hatches.
- Approved submittals / equipment IDs and calibration: ____________________
Prerequisites and work sequence
- Prior-work release / interfaces / access / pre-task briefing: ____________________
- 1. Coordinate module and access.
- 2. Install to correct orientation.
- 3. Verify movement before balancing.
Inspection stages and required records
- Checks and evidence: Tags, actuator operation, airflow settings and access.
- Before / during / final inspection: area, acceptance clause, frequency, hold or witness point and record reference: ____________________
- Nonconformance / corrective action / retest reference: ____________________
Approval
- Prepared by / reviewed by / approved by / signatures and dates: ____________________