ACT-104 / CHK / R00
Grilles, Diffusers and Dampers — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Coordinate module and access | — | — | — | — | — |
| Install to correct orientation | — | — | — | — | — |
| Verify movement before balancing | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: terminals, dampers, fixings and access hatches
Inspection points
- Coordinate module and access
- Install to correct orientation
- Verify movement before balancing
Records and release
- Tags, actuator operation, airflow settings and access
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________