ACT-100 / CHK / R00
AHU / FAHU Installation — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Confirm plinth and lifting access | — | — | — | — | — |
| Align section order | — | — | — | — | — |
| Connect duct, piping and condensate | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: AHU sections, mounts, filters and flexible connectors
Inspection points
- Confirm plinth and lifting access
- Align section order
- Connect duct, piping and condensate
Records and release
- Nameplate, alignment, filters, drain fall and start-up evidence
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________