ACT-097 / RA / R00
Hydrostatic Pressure Testing of Piping — Risk Assessment
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Task | Hazard and persons exposed | Initial risk | Controls | Owner | Residual risk |
|---|---|---|---|---|---|
| Define rated boundary | — | — | — | — | — |
| Document venting and protection | — | — | — | — | — |
| Witness authorised test and depressurisation | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: calibrated gauges, pump and isolation equipment
Task risk review
- Define rated boundary
- Document venting and protection
- Witness authorised test and depressurisation
Assessment prompts
- Assess interfaces relevant to this location: Stored energy, access and equipment handling.
- For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
- Briefing / permit reference / competent reviewer / approval date: ____________________