Hydrostatic Pressure Testing of Piping — Inspection Checklist

Hydrostatic Pressure Testing of PipingHVAC

ACT-097 / CHK / R00

Hydrostatic Pressure Testing of Piping — Inspection Checklist

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Inspection Checklist worksheet
Inspection pointAcceptance referenceObservationPass / Fail / N/AEvidenceInspector / date
Define rated boundary—————
Document venting and protection—————
Witness authorised test and depressurisation—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: calibrated gauges, pump and isolation equipment

Inspection points

  • Define rated boundary
  • Document venting and protection
  • Witness authorised test and depressurisation

Records and release

  • Approved pressure and duration, gauge IDs, readings and leakage
  • Record observed condition, acceptance reference, result and evidence for each item.
  • Inspector / witness / date / corrective action and reinspection: ____________________