Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Verify class and shop sizes—————
Fabricate and seal sections—————
Install supports before closure—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: duct sections, flanges, sealants and hangers

Inspection sequence

  • Verify class and shop sizes
  • Fabricate and seal sections
  • Install supports before closure

Inspection controls

  • Duct sizes, joints, clearances and leakage release
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________