Skip to content

Method StatementACT-061-MSR00Available

Floor Screeding Method Statement

Floor ScreedingArchitectural

ACT-061 / MS / R00

Floor Screeding Method Statement

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Scope and prerequisites

  • Identify bonded, unbonded or floating screed type and approved build-up. Do not substitute the system without approval.
  • Record approved specification, mix, primer, reinforcement, thickness and tolerances: ____________________
  • Assign screeding supervisor, installer and QC. Verify base release, services protection and level survey.

Work and inspection sequence

  • Set screed rails to finish datum and verify thresholds, falls and edge isolation before placement.
  • Prepare base and apply approved bond coat or separation layer as specified; inspect concealed build-up before placing.
  • Place and compact within approved working time, strike off to rails, finish and form joints in approved positions.
  • Protect and cure as specified. Verify levels, flatness, falls and required moisture before releasing for tile installation.

Records and approval

  • Mix tickets / location and level survey / curing record / screed release: ____________________
  • Prepared / reviewed / approved by and date: ____________________

Preview shown in full. The downloaded DOCX, XLSX and PDF are generated from this record.