ACT-061 / MS / R00
Floor Screeding Method Statement
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
Scope and prerequisites
- Identify bonded, unbonded or floating screed type and approved build-up. Do not substitute the system without approval.
- Record approved specification, mix, primer, reinforcement, thickness and tolerances: ____________________
- Assign screeding supervisor, installer and QC. Verify base release, services protection and level survey.
Work and inspection sequence
- Set screed rails to finish datum and verify thresholds, falls and edge isolation before placement.
- Prepare base and apply approved bond coat or separation layer as specified; inspect concealed build-up before placing.
- Place and compact within approved working time, strike off to rails, finish and form joints in approved positions.
- Protect and cure as specified. Verify levels, flatness, falls and required moisture before releasing for tile installation.
Records and approval
- Mix tickets / location and level survey / curing record / screed release: ____________________
- Prepared / reviewed / approved by and date: ____________________