ACT-058 / ITP / R00
Blockwork (Hollow / Solid / AAC) — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Set out courses | — | — | — | — | — |
| Coordinate openings and restraints | — | — | — | — | — |
| Protect masonry before finishing | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: specified blocks, mortar, ties and lintels
Inspection sequence
- Set out courses
- Coordinate openings and restraints
- Protect masonry before finishing
Inspection controls
- Block type, joints, plumb and lintel release
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________