ACT-052 / CHK / R00
High-Strength Bolting Works — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Confirm grades and faying surfaces | — | — | — | — | — |
| Tighten by approved method | — | — | — | — | — |
| Inspect designated connections | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: specified bolt assemblies and calibrated tools
Inspection points
- Confirm grades and faying surfaces
- Tighten by approved method
- Inspect designated connections
Records and release
- Bolt lot, tool calibration and pretension verification
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________