Mechanical Couplers (Rebar Splicing) — Inspection and Test Plan

Mechanical Couplers (Rebar Splicing)Structural

ACT-034 / ITP / R00

Mechanical Couplers (Rebar Splicing) — Inspection and Test Plan

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Verify compatible bars—————
Inspect ends—————
Assemble under approved supplier method—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: couplers, prepared bar ends and inspection tools

Inspection sequence

  • Verify compatible bars
  • Inspect ends
  • Assemble under approved supplier method

Inspection controls

  • Lot, engagement or torque, sample tests and concealment release
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________

Preview shown in full. The downloaded DOCX, XLSX and PDF are generated from this record.