ACT-020 / TEST / R00
Pile Integrity Test Witness Record
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
Test identification
- Pile ID / cut-off level / casting date / diameter / installed length / drawing revision: ____________________
- Approved test method and acceptance criteria / equipment ID and calibration / head preparation: ____________________
Evidence and disposition
- Trace file and impact positions / repeatability notes / exclusions / specialist interpretation report: ____________________
- The witness does not infer capacity from the integrity trace. Record reviewer disposition and any confirmatory tests: ____________________
- Operator / witness / consultant / dates: ____________________