Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Recover control—————
Close an independent traverse—————
Transfer grid and levels to protected marks—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: total station, level and benchmark markers

Inspection sequence

  • Recover control
  • Close an independent traverse
  • Transfer grid and levels to protected marks

Inspection controls

  • Coordinates, survey closure and instrument calibration
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________