ACT-141 / ITP / R00
Lightning Protection System — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Coordinate roof and separation | — | — | — | — | — |
| Install accessible links | — | — | — | — | — |
| Check conductor continuity | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: roof terminals, conductors, bonds and test links
Inspection sequence
- Coordinate roof and separation
- Install accessible links
- Check conductor continuity
Inspection controls
- Roof layout, bonded items and resistance results
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________