Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Coordinate roof and separation—————
Install accessible links—————
Check conductor continuity—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: roof terminals, conductors, bonds and test links

Inspection sequence

  • Coordinate roof and separation
  • Install accessible links
  • Check conductor continuity

Inspection controls

  • Roof layout, bonded items and resistance results
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________