ACT-141 / CHK / R00
Lightning Protection System — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Coordinate roof and separation | — | — | — | — | — |
| Install accessible links | — | — | — | — | — |
| Check conductor continuity | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: roof terminals, conductors, bonds and test links
Inspection points
- Coordinate roof and separation
- Install accessible links
- Check conductor continuity
Records and release
- Roof layout, bonded items and resistance results
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________