Risk AssessmentACT-120-RAR00Available

Fire Pumps Installation — Risk Assessment

Fire Pumps InstallationFirefighting

ACT-120 / RA / R00

Fire Pumps Installation — Risk Assessment

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Risk Assessment worksheet
TaskHazard and persons exposedInitial riskControlsOwnerResidual risk
Release foundation and access—————
Coordinate suction and discharge—————
Witness authorised tests—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: fire pumps, listed controllers and test header

Task risk review

  • Release foundation and access
  • Coordinate suction and discharge
  • Witness authorised tests

Assessment prompts

  • Assess interfaces relevant to this location: System impairment, stored energy and occupied-area interfaces.
  • For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
  • Briefing / permit reference / competent reviewer / approval date: ____________________

Preview shown in full. The downloaded DOCX, XLSX and PDF are generated from this record.