ACT-117 / CHK / R00
Drainage Water Test / Flow Test — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Define test section | — | — | — | — | — |
| Verify containment | — | — | — | — | — |
| Witness approved filling or discharge | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: approved plugs, water supply and level instruments
Inspection points
- Define test section
- Verify containment
- Witness approved filling or discharge
Records and release
- Water head or flow, leakage, drain time and retest
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________