Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Confirm isolation and disposal plan—————
Document specialist circulation—————
Sample designated points—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: approved chemicals, temporary hoses and sampling kits

Inspection sequence

  • Confirm isolation and disposal plan
  • Document specialist circulation
  • Sample designated points

Inspection controls

  • Chemical batch, circuit results, approved limits and effluent disposition
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________