ACT-103 / CHK / R00
Ventilation and Exhaust Fans — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Confirm orientation and duty | — | — | — | — | — |
| Mount and isolate vibration | — | — | — | — | — |
| Release electrical interfaces | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: fans, isolators, flexible connections and guards
Inspection points
- Confirm orientation and duty
- Mount and isolate vibration
- Release electrical interfaces
Records and release
- Airflow direction, rotation, guards and performance
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________