Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Check glass specification, orientation and edges—————
Place on supports—————
Complete retention—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: labelled glass, blocks, gaskets and lifting tools

Inspection sequence

  • Check glass specification, orientation and edges
  • Place on supports
  • Complete retention

Inspection controls

  • Unit locations, markings, edge condition and installation checks
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________