ACT-085 / ITP / R00
Glazing Works — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Check glass specification, orientation and edges | — | — | — | — | — |
| Place on supports | — | — | — | — | — |
| Complete retention | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: labelled glass, blocks, gaskets and lifting tools
Inspection sequence
- Check glass specification, orientation and edges
- Place on supports
- Complete retention
Inspection controls
- Unit locations, markings, edge condition and installation checks
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________