ACT-069 / ITP / R00
External Painting — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Release substrate and weather | — | — | — | — | — |
| Protect glazing | — | — | — | — | — |
| Apply approved coats by elevation | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: exterior coating, primer and access equipment
Inspection sequence
- Release substrate and weather
- Protect glazing
- Apply approved coats by elevation
Inspection controls
- Weather, coverage and finish consistency
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________