Work Inspection RequestACT-056-WIRR00Available

Roof Drain and Membrane Interface Checklist

Roof Waterproofing and InsulationStructural

ACT-056 / WIR / R00

Roof Drain and Membrane Interface Checklist

Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.

Before covering

  • Roof zone / outlet tag / drawing and revision: ____________________
  • Confirm outlet body is restrained, recessed to the drainage datum and compatible with the approved membrane system.
  • Verify substrate dryness, flange preparation, primer and local reinforcement against approved details.

Interface and test release

  • Inspect continuity around the flange, clamping ring or approved termination, lap positions and upstand transitions.
  • Record approved lap, termination and flood-test criteria: ____________________
  • Photograph interface before protection; record evidence and separate stormwater inspection reference: ____________________
  • Result / remarks / contractor and consultant signatures: ____________________