ACT-033 / CHK / R00
Reinforcement Steel Fixing — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Verify bar marks | — | — | — | — | — |
| Set cages and splices | — | — | — | — | — |
| Coordinate openings before closure | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: rebar, tying wire, spacers and chairs
Inspection points
- Verify bar marks
- Set cages and splices
- Coordinate openings before closure
Records and release
- Bar heat, grade, spacing, laps and cover
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________