ACT-027 / CHK / R00
Backfilling and Compaction — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Release retaining interfaces | — | — | — | — | — |
| Place approved lifts | — | — | — | — | — |
| Test lots before next lift | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: approved fill, moisture control and compaction plant
Inspection points
- Release retaining interfaces
- Place approved lifts
- Test lots before next lift
Records and release
- Fill source, lift thickness, moisture, density and rework
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________