ACT-025 / CHK / R00
Raft Foundation Construction — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Release substrate and membrane | — | — | — | — | — |
| Coordinate raft rebar and embeds | — | — | — | — | — |
| Secure pre-pour release | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: rebar, spacers, sleeves, waterstops and concrete
Inspection points
- Release substrate and membrane
- Coordinate raft rebar and embeds
- Secure pre-pour release
Records and release
- Cover, embed locations, concrete tests and raft survey
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________