ACT-005 / RA / R00
Temporary Power and Water Supply — Risk Assessment
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Task | Hazard and persons exposed | Initial risk | Controls | Owner | Residual risk |
|---|---|---|---|---|---|
| Identify supply boundaries | — | — | — | — | — |
| Route protected segregated services | — | — | — | — | — |
| Obtain authorised connection and tests | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: distribution panels, hoses and backflow fittings
Task risk review
- Identify supply boundaries
- Route protected segregated services
- Obtain authorised connection and tests
Assessment prompts
- Assess interfaces relevant to this location: Moving plant, temporary services and public access.
- For each task identify hazards, persons exposed, initial rating, controls, responsible person and residual rating using the project risk matrix.
- Briefing / permit reference / competent reviewer / approval date: ____________________