Inspection and Test Plan worksheet
Inspection stageCriteria / clauseFrequencyResponsibilityIntervention pointEvidence
Approve vein layout and supports—————
Fit and align stone—————
Protect finish—————

Work identification

  • Project / area / grid: ____________________
  • Approved method, drawing and specification revisions: ____________________
  • Equipment and materials in scope: stone units and approved anchors or adhesives

Inspection sequence

  • Approve vein layout and supports
  • Fit and align stone
  • Protect finish

Inspection controls

  • Slab marks, colour consistency, joints and support inspection
  • Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
  • Project review and approval: ____________________