ACT-044 / ITP / R00
Concrete Repair Works — Inspection and Test Plan
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection stage | Criteria / clause | Frequency | Responsibility | Intervention point | Evidence |
|---|---|---|---|---|---|
| Map defects | — | — | — | — | — |
| Agree repair class | — | — | — | — | — |
| Release substrate and cure repaired area | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: approved repair system and preparation tools
Inspection sequence
- Map defects
- Agree repair class
- Release substrate and cure repaired area
Inspection controls
- Depth and extent, materials and verification results
- Enter the approved acceptance clause, inspection frequency, responsible party and hold or witness point for each stage.
- Project review and approval: ____________________