ACT-040 / CHK / R00
Construction Joints and Waterstops — Inspection Checklist
Fictional demonstration project: SiteQuality Courtyard. Adapt to the approved project documents before use.
| Inspection point | Acceptance reference | Observation | Pass / Fail / N/A | Evidence | Inspector / date |
|---|---|---|---|---|---|
| Confirm joint positions | — | — | — | — | — |
| Secure waterstop before pour | — | — | — | — | — |
| Review visible splice before closure | — | — | — | — | — |
Work identification
- Project / area / grid: ____________________
- Approved method, drawing and specification revisions: ____________________
- Equipment and materials in scope: waterstop, restraints and approved splicing kit
Inspection points
- Confirm joint positions
- Secure waterstop before pour
- Review visible splice before closure
Records and release
- Location, splice integrity and photos on both faces
- Record observed condition, acceptance reference, result and evidence for each item.
- Inspector / witness / date / corrective action and reinspection: ____________________