29 activities
Search the document libraryConcrete StructureActivities: 22
Formwork for Columns and Walls
Structural · During Construction
Inspection covers dimensions, plumb, cleanout and pre-pour approval.
Formwork for Slabs and Beams
Structural · During Construction
Inspection covers camber, levels, support layout and opening protection.
Core Wall Jump Form / Climbing Form System
Structural · During Construction
Inspection covers anchor IDs, platform release and cycle configuration.
Table Form / Flying Form System
Structural · During Construction
Inspection covers table ID, lifting points and receiving-bay survey.
Reinforcement Steel Fixing
Structural · During Construction
Inspection covers bar heat, grade, spacing, laps and cover.
Mechanical Couplers (Rebar Splicing)
Structural · During Construction
Inspection covers lot, engagement or torque, sample tests and concealment release.
Concrete Pouring (General)
Structural · During Construction
Inspection covers tickets, consistency, temperature, sample IDs and pour card.
Mass Concrete Pouring (Raft)
Structural · During Construction
Inspection covers probe IDs, temperature curves, approved limits and deviations.
Concrete Pumping Works
Structural · During Construction
Inspection covers line inspection, restraint, approved setup and washout disposal.
Hot Weather Concreting
Structural · During Construction
Inspection covers ambient and load temperature, elapsed time and rejection evidence.
Concrete Curing
Structural · During Construction
Inspection covers timing, coverage, interruptions and curing release.
Construction Joints and Waterstops
Structural · During Construction
Inspection covers location, splice integrity and photos on both faces.
Post-Tensioned Slabs
Structural · During Construction
Inspection covers tendon IDs, elongation, jack calibration and closure evidence.
Precast Concrete Elements Installation
Structural · During Construction
Inspection covers piece marks, bearing length, restraint and connection evidence.
Hollow Core Slab Installation
Structural · During Construction
Inspection covers seat lengths, unit damage and opening restrictions.
Concrete Repair Works
Structural · During Construction
Inspection covers depth and extent, materials and verification results.
Core Drilling and Coring Tests
Structural · During Construction
Inspection covers scan, orientation, custody, lab results and repair.
Embedded Items and Sleeves Installation
Structural · During Construction
Inspection covers coordinates, level, rotation and rebar clearance.
Staircase Construction
Structural · During Construction
Inspection covers rise, going, landings and edge protection.
Shear Walls and Lift Cores
Structural · During Construction
Inspection covers core verticality, shaft dimensions and embedded brackets.
Water Tanks (Concrete) Construction
Structural · During Construction
Inspection covers joint continuity, level observations and leak disposition.
Formwork Striking and Removal
Structural · During Construction
Inspection covers strength evidence, time, retained support and condition.
Structural Steel & RoofActivities: 7
Structural Steel Erection
Structural · During Construction
Inspection covers piece marks, baseplate levels, plumb and stability release.
High-Strength Bolting Works
Structural · During Construction
Inspection covers bolt lot, tool calibration and pretension verification.
Site Welding Works
Structural · During Construction
Inspection covers weld map, consumable lot, NDT and repair history.
Metal Deck Installation
Structural · During Construction
Inspection covers laps, supports, fixing pattern and pre-pour release.
Fire-Proofing Paint (Intumescent) for Steel
Structural · During Construction
Inspection covers batch, ambient condition, film thickness and fire rating reference.
Roof Waterproofing and Insulation
Structural · During Construction
Inspection covers laps, thickness, flood-test evidence and concealed photographs.
Green Roof / Roof Finishes
Structural · During Construction
Inspection covers media depth, drainage continuity and planting handover.